Renovating a NYC Co-op or Condo: Alteration Agreements and Permits Explained

Vitutti Construction

Narrow white kitchen with gray countertops, stainless appliances and a wood-look floor

Renovating an apartment in a co-op or condo adds a layer that houses don’t have: the building itself. Understanding that process early saves weeks of waiting.

Two approvals, not one

Most apartment renovations need the building’s approval, and some also need a NYC Department of Buildings (DOB) permit. They are separate: the building can require approval even for work the city doesn’t permit, and a permit doesn’t replace the building’s rules.

The alteration agreement

Most co-ops and many condos ask for an alteration agreement before work begins. It usually covers:

  • a description and drawings of the work
  • the contractor’s license and a certificate of insurance naming the building
  • working hours, noise limits and rules for deliveries and elevators
  • a deposit, and who pays for any damage to common areas
  • sometimes a review by the building’s architect or engineer

Some buildings also have “summer rules” that allow major work only in certain months. Ask your managing agent for the building’s alteration package as soon as you start planning.

When the city requires a permit

Under DOB rules, replacing finishes and fixtures in the same place generally does not need a permit. Work that changes systems or structure does, for example:

  • moving or adding plumbing, or rerouting gas lines (done under a Licensed Master Plumber)
  • adding electrical circuits (done by a licensed electrician)
  • removing or adding walls, or adding a bathroom

Depending on the scope, the filing is made by a licensed professional such as an architect, engineer or Licensed Master Plumber. Check the DOB’s current guidance or ask us what applies to your plans.

How to keep the schedule moving

  • Get the alteration package first and plan the scope around its rules.
  • Choose finishes before you submit, so the scope doesn’t change after approval.
  • Ask for a written scope of work you can attach to the board package.
  • Build board review time into your schedule; it is often the longest wait.

We provide our license, insurance certificates and a detailed scope of work for your board package, and plan the work around your building’s hours and rules.

Common mistakes to avoid

  • starting demolition before the building has approved the work
  • planning a layout the building does not allow, such as a bathroom above a neighbor’s living room
  • hiring a contractor who cannot provide the insurance certificates the building requires
  • changing the scope after approval, which can send the plans back for another review